Output of the Paks nuclear power plant’s Block 1 was back at 100% early in the afternoon on Friday after a control system malfunction was corrected, a plant official said. The block was automatically shut down on Thursday morning due to the malfunction.

Paks communications director Antal Kovács said the block was re-started in the morning on Friday and reached its nominal 500MW capacity at 2:20 in the afternoon.

The cause of the malfunction will be reviewed, as required by law, Gyula Fichtinger, the head of the National Atomic Energy Office (OAH), told MTI.