Photos: Budapest Nyugati Railway Station In Worse Shape Than Thought
- 17 Nov 2020 8:33 AM
- Hungary Around the Clock

As a result, the renovation work will take six months longer than expected, said state railway company MÁV.
Precipitation has damaged the walls so much that local repairs are not a permanent solution, so the interior masonry must be renovated over a 1,210m2 area.
Another problem is that the internal plinth stones, windows and doors have to be refurbished.
The roof structure of the building is 143 years old. Due to the defects now discovered, additional works had to be ordered, therefore the renovation of the station can only be completed by the summer of 2021.