Tram Project Much Delayed In Debrecen, Hungary
- 1 Jun 2012 9:00 AM
- getting around
The city of Debrecen will formally file a request today for a daily Ft 10 million indemnity payment from project managers who are far behind schedule on building a second tram line in the city. Mayor Lajos Kósa told a Thursday press conference that the ATK-Debrecen consortium was to have completed the project on May 31, but only 23% of the track and 32-33% of the terminal is completed.
Tram Project Much Delayed In Debrecen, Hungary
- 1 Jun 2012 9:00 AM
- getting around
The city of Debrecen will formally file a request today for a daily Ft 10 million indemnity payment from project managers who are far behind schedule on building a second tram line in the city. Mayor Lajos Kósa told a Thursday press conference that the ATK-Debrecen consortium was to have completed the project on May 31, but only 23% of the track and 32-33% of the terminal is completed.